Contract Overview
Start Date: November 2009
End Date: January 2009
Contract Value: $400,000 – $600,000

Sub-Contractors & Project Roles
Commercial Trenching (CTL Canada)

Scope of Work

  • Directional drilled from Fort Edmonton Park to SW Eco Centre, approximately 11km
  • Designed, supplied, installed, terminated and tested backbone FOC as per requirements
  • Completed spur distribution for approximately 5 buildings
  • Designed fibre ring for future scalability
  • Performed the role of General Contractor & Prime for the duration of the project
  • Chermik supplied electrical requirements for all building entrances
  • Performed all splicing, terminations, and testing of installed fibre optic cable
  • Maintained QA/QC standards for all work performed