Agrium Fort Saskatchewan – 5KV Pole Line Disconnect & Replacement

Agrium Fort Saskatchewan – 5KV Pole Line Disconnect & Replacement

Agrium Fort Saskatchewan – 5KV Pole Line Disconnect & Replacement
Client: Agrium Canada Inc.

Contract Overview
Start Date: October 2013
End Date: December 2013
Contract Value: Available upon request

Sub-Contractors & Project Roles
Platinum Engineering, Specialty Testing

Scope of Work

  • Cutover of existing overhead disconnects onto new platform mounted disconnects
  • Installed additional pole anchors and removed redundant overhead power lines
  • Installation, termination, and testing of three 5kv disconnect cubicals
  • Installation of new outdoor cable tray above grade, and 5kv teck cables including grounding