LRT Conveyance & NE Fibre Upgrades

LRT Conveyance & NE Fibre Upgrades

LRT Conveyance & NE Fibre Upgrades
Client: City of Edmonton

Contract Overview
Start Date: May 2010
End Date: December 2010
Contract Value: 1.0M – 2.0M

Sub-Contractors & Project Roles

N/A

Scope of Work

  • Conveyance Pathways & multi-use fibre along LRT ROW, inside live LRT tunnels, building ties and inside stations
  • Design, supply, and install upwards of 2.75km of open rung cable tray, 2.0km of 4” rigid galvanized steel conduit within all below ground infrastructure locations between Churchill LRT station and North Portal for fibre optic and signaling cables
  • Fibre design, supply, placement, termination, and testing. CAD as built design, and documentation
  • Install 8.5km of 216F backbone fibre cable, plus multiple spurs for distribution for signaling, LRT operations, and City of Edmonton IT usage
  • Furnished 20 year Superior Essex manufacturer’s warranty on complete OSP installation